Premium restaurant build-outs that open on the date we committed to.
QSR, fast-casual, full-service, and bar-forward build-outs across the Western U.S. Kitchen MEP expertise, AHJ-fluent permitting, GMP cost certainty, and a documented opening-date track record.
Lease signed or in LOI? Get a class-3 estimate range within 3–5 business days.
Request a consultationA defensible timeline from lease signing to opening.
A typical restaurant build-out runs 6–11 months. The variance is driven by permitting queues, equipment lead times, and how early the kitchen scope is locked. We sequence work so the critical path is the critical path — not surprises.
Preconstruction & design
8–14 weeks
Programming, kitchen layout, MEP basis-of-design, GMP cost model.
Permitting
4–10 weeks
Building + health + fire submitted in parallel. AHJ pre-submittal meetings.
Long-lead equipment
8–22 weeks
Hoods, walk-ins, refrigeration, and brand-specific equipment released at DD.
Construction
12–22 weeks
Self-perform critical path. Weekly schedule and cost reporting against the GMP.
Inspections & soft-open
2–3 weeks
Building / fire / health finals, equipment commissioning, soft-open punch.
What restaurant build-outs cost per square foot in 2026.
Benchmarks below reflect 2026 western-U.S. pricing for ground-up shells delivered to vanilla and TI build-outs in standard centers. Site-driven scope — utility upgrades, ADA path-of-travel, grease interceptor — can swing 10–25%. Kitchen MEP is the largest line item in every category.
QSR / Fast food
$325–$525/SF
Limited FOH, standardized kitchen package, drive-thru where applicable.
Fast-casual
$375–$625/SF
Open kitchen, mid-density FOH finishes, full prep line.
Full-service casual
$425–$725/SF
Full bar, expanded prep, dish, and walk-in scope, higher FOH density.
Upscale & chef-driven
$550–$900+/SF
Custom millwork, premium finishes, dedicated bar program, often live-fire cooking.
Ghost kitchen / Commissary
$275–$450/SF
Reduced FOH; kitchen MEP scope similar to dine-in.
Permitting fluency is the difference between opening on time and missing the window.
Restaurants run through more permit reviews than any other commercial category. We submit building, health, and fire in parallel, pre-meet plan reviewers, and sequence inspections against the soft-open date — not the other way around.
Building permit
Architectural / structural / MEP
Submitted with sealed plans; review 3–8 weeks first cycle in most western AHJs.
Health department
Plan review + final inspection
Separate queue from building. Pre-submittal meeting saves 3–6 weeks.
Fire / suppression
Type-I hood + Ansul
Engineered submittal, smoke test, alarm tie-in coordinated with landlord systems.
ABC / liquor
If serving alcohol
State and local; can run 60–120+ days — start at lease signing, not construction start.
ADA accessibility
Path of travel, restrooms, parking
Older centers often trigger upgrades outside the tenant suite — a frequent cost surprise.
Kitchen layout drives every downstream cost.
Equipment count, hood length, make-up air, gas service, plumbing rough-in, refrigeration, and throughput per labor hour all flow from layout. Lock the kitchen at SD — changes after permit cost 5–15× what they cost during schematic design.
Cook line
Hood + make-up air sized to equipment
Type-I hood over grease-producing equipment; MUA balanced within code tolerance.
Refrigeration
Walk-in + reach-in + prep rails
Compressor location, condensate management, and electrical load planned at DD.
Dish & sanitation
Three-comp sink, high-temp dish, mop sink
Indirect waste, grease interceptor sizing, high-temp electrical and venting.
Prep & dry storage
Hand sinks at every station
Health-department-prescribed; finish package (FRP, coved base, washable ceilings) drives cost.
FOH & bar
Service flow + ADA seating
Drink rail plumbing, glycol lines for draft, POS rough-in, and accessible bar where service occurs.
The questions every operator asks before signing a contract.
We answer the most common restaurant build-out questions in detail — planning, permits, construction logistics, budgeting, and post-build operations.
Read the full FAQHow long does a restaurant build-out take from lease signing to opening?
A typical restaurant build-out runs 6–11 months end-to-end: 8–14 weeks of preconstruction and design, 4–10 weeks of permitting (longer where health-department review queues are deep), 12–22 weeks of construction, and 2–3 weeks of inspections, equipment commissioning, and soft-open. QSR and fast-casual prototypes land at the low end; full-service and chef-driven concepts at the high end.
How much does a restaurant build-out cost per square foot?
2026 benchmarks: QSR $325–$525/SF, fast-casual $375–$625/SF, full-service casual $425–$725/SF, upscale and chef-driven $550–$900+/SF. Ghost kitchens and commissaries run $275–$450/SF. Kitchen MEP — hood, make-up air, gas, grease, refrigeration — is the single largest cost driver in every category.
Do I need an architect for a restaurant build-out?
Yes. Every jurisdiction requires sealed architectural and MEP drawings for a commercial restaurant permit. On design-build delivery we contract the architect and engineers under one agreement so the owner has a single accountable party. On design-bid-build, the owner contracts the architect separately and the GC bids the completed drawings.
How important is the kitchen layout?
It is the most important decision in the project. Kitchen layout drives equipment count, hood length, make-up air sizing, gas line capacity, plumbing rough-in, refrigeration loads, and ultimately throughput per labor hour. Layout changes after permit cost 5–15× what they cost during schematic design — lock the kitchen at SD, not at CDs.
What permits do I need for a restaurant build-out?
At minimum: a building permit (architectural, structural, MEP), a separate health-department plan review and permit, a fire / fire-suppression permit for the Type-I hood and Ansul system, an ABC / liquor permit if serving alcohol, and a sign permit. Some jurisdictions add grease-interceptor permits, food-handler certification, and zoning use permits.
Talk to our restaurant team.
Share the site, the concept, and the target opening date. We respond within one business day with the next concrete step — a class-3 estimate range, a kitchen-layout review, or an AHJ permit-strategy call.
- Class-3 estimate range in 3–5 business days
- Kitchen-MEP and AHJ permit-strategy review
- GMP commitment before mobilization
- Single accountable team — design, kitchen, and construction
