Back to blog
June 30, 2026 · Frans Construction

Commercial Construction Timeline: From Bid to Certificate of Occupancy

A realistic phase-by-phase timeline for commercial construction projects — preconstruction, permitting, construction, and closeout — with typical durations and the levers that compress schedule.

Overhead view of architectural blueprints, calendar, hard hat, and laptop on a construction planning table

Owners ask "how long?" before "how much?" — and for good reason. A delayed opening costs rent, payroll, debt service, and brand momentum. Below is a realistic, phase-by-phase commercial construction timeline with the durations we plan against on real projects, and the levers that compress schedule when the calendar matters.

The Full Commercial Construction Timeline

PhaseTypical durationWhat happens
Preconstruction4 – 10 weeksProgramming, conceptual estimating, site due diligence, delivery-model selection
Design8 – 20 weeksSD → DD → CDs, MEP coordination, owner sign-offs
Permitting / AHJ review4 – 16 weeksPlan check, corrections, health, fire, ADA, energy code
Bidding / GMP3 – 6 weeksSub bids, value engineering, GMP commitment
Mobilization1 – 2 weeksSite logistics, utilities, fencing, deliveries
Construction12 – 36 weeksDemo → structure → MEP rough → finishes → equipment
Inspections & closeout2 – 4 weeksFinal inspections, punch list, TCO/CO, owner training
Total (TI)4 – 7 monthsTenant improvements inside existing shells
Total (ground-up retail / restaurant)7 – 12 monthsPad through opening
Total (healthcare TI)6 – 12 monthsAdds OSHPD / state hospital review
Total (ground-up healthcare)14 – 30 monthsHospital additions and full facilities

Phase Detail

Preconstruction (weeks 1–10)

This is where schedule certainty is actually won. A disciplined preconstruction workflow — site investigation, conceptual estimating against SD documents, AHJ pre-application meetings, long-lead identification — kills the surprises that derail mid-project schedules. Skipping preconstruction to "get into the field faster" is the most common cause of multi-month overruns.

Design (weeks 4–24, often overlapping)

Design-bid-build runs design and construction in series. Design-build runs them in parallel — architecture, engineering, and construction collaborate from day one, so MEP coordination and constructability reviews happen during DD, not as RFIs during framing. On most projects, design-build compresses the total schedule 15–30%.

Permitting (weeks 12–28, AHJ-dependent)

Permit duration varies dramatically by jurisdiction. A retail TI in a fast-turn city may permit in 4 weeks; the same scope in a slow plan-check market can take 16. Healthcare adds state-level review (e.g. OSHPD, HCAi). Build the permitting calendar from the AHJ's published timelines, not a generic average.

Construction (weeks 16–52)

Construction duration is driven by structural scope, MEP density, and finish complexity. Self-performing concrete, framing, or finishes pulls those crews onto your critical path under direct control — instead of waiting on a subcontractor's schedule. For multi-site retail programs, concurrent execution across markets is the schedule lever that matters most.

Closeout (weeks 50+)

Closeout is where mediocre contractors lose 2–4 weeks. Disciplined contractors build the punch list weekly during finishes, schedule final inspections before they're needed, and walk owner training before substantial completion. The result: TCO or CO on the date committed at GMP signature.

Levers That Compress the Schedule

  • Design-build delivery — overlap design and construction (15–30% faster).
  • Early procurement — release long-lead items (switchgear, RTUs, custom millwork, kitchen equipment) at DD instead of CDs.
  • Self-perform crews — direct control over critical-path trades.
  • AHJ pre-submittal meetings — fewer plan-check cycles.
  • Phased construction — open core space while finishing perimeter.
  • Concurrent multi-site execution — for rollouts, run sites in parallel rather than series.

Levers That Stretch the Schedule

  • Late scope changes that trigger redesign and re-permit
  • Owner-supplied equipment without lead-time coordination
  • Underestimating AHJ review duration
  • Designing without subcontractor input on means and methods
  • Selecting the low bid from a sub that's already overcommitted

Build a Schedule, Not a Wish

A committed schedule is the deliverable of preconstruction — not a guess on the kickoff call. We build durations bottom-up from trade-by-trade quantities, AHJ-specific review timelines, and committed lead times, then commit to that schedule in the GMP.

Related reading: Commercial construction cost per square foot · How to choose a commercial general contractor

Ready to Build a Real Timeline?

Request preconstruction support and we will return a project-specific schedule with AHJ assumptions and long-lead callouts within five business days.

Plan your next project

Request a consultation with Frans Construction

Talk to our preconstruction team about your commercial buildout, multi-state rollout, or design-build project. Most clients hear back within one business day.